Click the thumbnail images to learn more about the progress of the HP garage property reconstruction. Each image links to a different slide show.
 October 31 The preservation and rehabilitation efforts officially wrap up. |
|

October 25 Landscaping gets underway; furniture is set up; the garage staining and painting is complete; and Bill and Dave's workbench is recreated.
|
| |
 October 18 Crowning touches are added: walkways, the landmark sign and a low-profile fence. |
|

October 11 Final touches are put on the house while the environmentally friendly driveway goes in and planning begins for recreating Bill and Dave's workbench.
|
| |
 October 3 The crew tackles the final stages inside, outside and all around the garage.
|
|

September 27 Paint is applied, cabinets and fixtures go up, baseboard and picture rail trim is installed, and a new patio gets poured.
|
| |
 September 20 With only a month to go, painters, carpenters, sheet rock installers, tapers and window hangers pick up momentum inside and out.
|
|
 September 13 Work is done on the back porch and wheelchair lift; the chimney nears completion; and insulation and sheetrock go up in the house's interior rooms. |
| |
 September 6 Work focuses on the house. Porch footings are poured, the first layer of trim paint goes on, clinker bricks climb up the chimney and the team leaves its mark. |
|
 August 30 The house gets new rain gutters, roof shingles and more doors. Forms are prepared for back porch steps and decorative touches begin to reappear. |
| |
 August 23 Porch steps are prepped; staircases, windows and doors go in; the shed is nearly complete; and the HP garage gets a new roof. |
|
 August 23 The reinforced chimney has its footing and firebox in place, and its steel support structure rises above the roofline. |
| |
 August 16 Another week of change rolls along as the shed gets cedar shingles and the house's second floor gets windows and custom rafter tail supports. |
|
 August 12 Progress in the house continues, along with preparations that will lead to a new, more accessible mounting for the landmark plaque. |
| |
 August 9 Work on the house includes the fireplace and front dormer. Meanwhile a trench reveals a mystery. |
|
 August 2 It's a week of detailed work on the garage and shed as they near completion. |
| |
 July 28 The shed and garage get paper roofs, the fireplace gets a foundation, plumbing and heating systems go in, and more. |
|
 July 21 A week of steady progress adds plywood sheathing, replacement rain gutters, and more. |
| |
 July 14 The house gets a new porch cover, electrical and plumbing, and the garage gets some weather proofing. |
|
 July 7 Reconstruction of the front porch begins. The porch area will return to its original open structure as it was in 1938.
|
| |
 June 30 The house window casings are reinstalled, framing completed on the back porch area, and the garage has its outer boards reattached.
|
|
 June 21 From the ground up, every building receives the respectful treatment it deserves, including an all important treatment for termites.
|
| |
 June 14 The garage's new concrete curb has been poured, and the teardown of an old barn nearby provides a batch of wood perfect for garage repairs. |
|
 June 2 While the moving crew lowers the house, the original rafters are recycled and repaired. |
|
| |
 June 2 With the foundation completely set, the house is lowered. |
|
 May 12 The day of the big concrete pour arrives. Once the concrete cures, the house can be lowered. |
| |
 April 27 The crew adds concrete reinforcing bar (rebar) to strengthen the foundation. |
|
 April 22 It's time to place the forms for the new foundation. |
| |
 April 18 Scheduled work begins on the roof of the garage. |
|
 April 13 The garage gets a privacy screen, and the shed undergoes final preparations. |
| |
 April 12 Deconstruction of the HP garage begins. |
|
 April 4 In a multistep process, the house is smoothly raised 4 feet off the ground. |
| |
 April 1 Structural engineers, site workers and house movers converge for the big setup. |
|
 March 25 Interior shoring and framing continues in preparation for "liftoff." |
| |
 March 14 Deconstruction of the chimney continues in a rush to beat the rain. |
|
 March 10 Deconstruction and cataloging of the clinker-brick chimney begins. |
| |
 March 7 The sun finally breaks through, and work outside begins again. |
|
 March 1 Rain and more rain ushers in the month. |
| |
 February 24 The house gives up a few more secrets - including hidden staircases. |
|
 February 22 Things begin to move fast, and more surprises emerge. |
| |
 February 8 Serious deconstruction begins on the back of the house. |
|
 February 4 The original floor plan and details of the house begin to emerge. |
| |
 January 19, 2005 Preservation and rehabilitation efforts are off and running. |
|
 December 17, 2004 Secrets of the original construction begin to emerge. |